
One of the first questions homeowners ask when planning a bathroom remodel is:
“How long is this going to take?”
This is a great question. Bathroom remodels temporarily disrupt your daily routine, and most people want to plan their lives around the project. The truth is, the timeline can vary depending on the size of the bathroom, the scope of work, and how well the project is planned and managed.
Below is a clear breakdown of what you can realistically expect.
Average Timeline: 3–6 Weeks for Most Bathrooms
For a standard bathroom remodel, the full process typically takes 3 to 6 weeks of active construction, assuming everything is well-coordinated and materials are ready.
Larger or more complex projects (moving plumbing, custom tile work, full layout changes) can take 6–10 weeks.
Phase-by-Phase Breakdown
1. Planning & Design – 1–3 Weeks (Sometimes Longer)
Before any hammer swings, you’ll spend time choosing materials, verifying measurements, and finalizing layout decisions.
This stage includes:
• Design consultations
• Material selections (tile, fixtures, vanity, etc.)
• Final budget approval
• Ordering materials
Timeline tip: Delays usually happen when selections are changed mid-project. Finalize early to stay on schedule.
2. Ordering & Lead Times – 1–4 Weeks
Some products arrive quickly, others can take several weeks.
Common longer lead items:
• Custom vanities
• Special-order tile
• Glass shower doors
• Luxury plumbing fixtures
A good contractor orders materials early and tracks deliveries to avoid holding up the schedule.
3. Demolition – 1–3 Days
Removing old fixtures, flooring, cabinets, and tile usually takes a couple of days.
Unexpected issues (water damage, mold, unlevel floors) can extend this phase.
4. Rough-In Work (Plumbing, Electrical, HVAC) – 3–7 Days
Once the bathroom is opened up, licensed trades update the “behind-the-walls” systems:
• Moving or updating plumbing lines
• Running electrical for lighting and outlets
• HVAC vents or exhaust fan work
Inspection scheduling can add time depending on the city.
5. Inspections – 1–5 Days
Most remodels require city inspections for:
• Plumbing rough-in
• Electrical rough-in
• Final inspection
Your contractor handles the scheduling, but availability varies by municipality.
6. Drywall & Texture – 2–4 Days
After passing inspections, drywall is installed, taped, mudded, and textured to match the existing home.
⸻
7. Flooring & Tile Work – 4–10 Days
Tile is one of the most time-consuming parts of the project, especially for custom shower designs or intricate patterns.
This phase includes:
• Waterproofing
• Shower pan or system installation
• Wall tile
• Floor tile
• Grout and drying time
8. Cabinetry, Trim & Painting – 2–5 Days
This stage brings the bathroom back to life:
• Installing the vanity
• Painting walls
• Installing trim or baseboards
9. Fixture Installation & Finishing Touches – 2–4 Days
Plumbers and electricians return for final hookups:
• Toilet
• Faucets
• Shower fixtures
• Lighting
• Exhaust fan
• Accessories (towel bars, mirrors, etc.)
10. Glass Shower Door (If Applicable) – Add 7–14 Days
Most shower doors can only be measured after tile is complete.
Once measured, fabrication typically takes a week or two.
This is one of the most common reasons why bathrooms take a little longer than homeowners expect.
Common Reasons Timelines Get Delayed
Even with a great contractor, delays can happen. The biggest causes include:
• Long material lead times
• Changing selections mid-project
• Unexpected plumbing/electrical issues
• Mold, rot, or water damage
• Delayed inspections
• Custom tile or custom cabinetry
Choosing a contractor with strong project management helps eliminate most of these issues before they start.
How We Keep Bathroom Remodels On Schedule
If you’re working with Building While Giving, here’s what we do to keep your remodel moving smoothly:
• We help finalize selections early
• We order materials before demolition
• We schedule trades and inspections efficiently
• We provide clear weekly updates
• We keep the jobsite clean and safe
The result? A smoother, faster remodel with fewer surprises.
Final Thoughts
A bathroom remodel is one of the best upgrades you can make to your home — and with the right preparation and contractor, the process doesn’t have to be stressful.
Typical timeline: 3–6 weeks
Complex projects: 6–10 weeks
Every bathroom is different, but clear communication and good planning make all the difference. If you're ready for a bathroom remodel, give us a call at (720) 968-7874
Have questions or ready to start your project? Fill out the form below and we'll get back to you promptly. We're here to help!